1. O. I. Z. Central Sewage Treatment Plant

Employer : DENİZLİ ÇARDAK ORGANIZED INDUSTRIAL ZONE DIRECTORATE (DENİZLİ CHAMBER OF INDUSTRY)
Location : Çardak/Denizli
Definition of the project : The Sewage Treatment Plant Construction of Denizli Organized Industrial Zone 1 is one of the biggest treatment plants made in the organized industrial zones. It is the construction of central sewage treatment plant consisting of physical (mechanical), chemical, biologica and sludge dewatering units with a capacity of 55.860 m³/day, equivalent to 280.000 population, over an area of 30.000 m². The project, completed in 11 months, made Turkish construction history in two important subjects (1. duration, 2. cost), which can be considered as record, as it took the "discharge" authorization from the Provincial Environment Department of Turkey Republic Denizli Governorship in a short period of 3 months.